19.11.2020
News
ZRF "RUMBA" completed the works on the object - Gas transmission branch to GRS Sloka renewal with pipe replacement in the section 22.6 km - 30.6 km
The total length of the gas branch on GRS "Sloka" is 30.6 km, of which 8.1 km have been rebuilt.
Main completed works:
- dismantling of existing pipes and reinforced concrete shutters along the construction length of a new gas pipeline section (L=8100 m)
- gas pipeline DN250, construction of a new section (L=8100 m)
- insulation of welded joints
- anti-corrosion and stray current protection of the gas pipeline